The Delta Xi Chapter alumnae leadership has developed a solid plan to address the long-term viability of the Tri Delta experience at Mizzou. Through careful study, assessment, and planning, it has been determined that a renovation and addition to our home are necessary to meet the needs of today’s students and to remain competitive on campus. Working with McAfee Construction of Columbia, the Delta Xi House Corporation has developed a tactical approach to our future. The project highlights below and plans outlined on the construction update page are designed to enhance the educational, personal, and professional experiences.

 

Project Highlights

Phase 1 (Completed 2010-11)

  • Fire-sprinkler/alarm system installation

 

Phase 2 (Summer 2013-Fall 2013)

  • Build addition on west side of home to relocate kitchen and dining to first floor
  • Create commercial-size kitchen necessary for meals and events
  • Expand dining room with 180 lecture/120 dining seating capacity—multi-use space
  • Build new patio
  • Create first floor bathroom with handicap accessibility along west wing
  • Renovate house director’s suite and president’s room, including new bathrooms
  • Create designated office space
  • Relocate computer room to basement level
  • Update and expand wireless technology

 

Phase 3 (Complete Summer 2014)

  • Demolish annex; use space for required parking
  • Add bedrooms for 14 in new west wing addition (occupancy = 92 after renovation)
  • Install new north parking lot (40+ spaces) and bike rack
  • Make minor common area renovations
  • Renovate second and third floor bathrooms
  • Transform basement and lower level kitchen areas into library, study and craft spaces
  • Build handicap accessible restroom

 